Task Glossary
Attribute | Read/Write | Description |
---|---|---|
Nom | RW | A short description. |
Démarrage Planifié | RW | The date at which the task is scheduled to start. |
Fin Planifiée | RW | The date at which the task is scheduled to finish. |
Planifié Manuellement | RW | Celoxis will never change the start and finish of manually scheduled tasks. Read More. |
Durée | RW | The duration of the task. It can be entered in these formats. Read More. |
Effort Planifié | RW | The total hours of effort required to complete the task. Read More. |
Type de planification | RW | One of FixedEffort, Durée fixe, Unités fixes. Read More |
Type de contrainte/Date de contrainte | RW | Task constraint. Not applicable for summary tasks and manually scheduled tasks. Read More. |
Ressources | RW | Resources assigned on the task. It can be entered in this format. |
% fin | RW | The percentage of work done. Read More. |
% Terminé Planifié | RW | The percentage that the task is expected to have completed by now. This value is an approximate value and will not be accurate if resources working on the task have working or non-working exceptions in the task duration. |
Priorité | RW | The task's priority. |
Permet la journalisation du temps | RW | Indicates if time can be logged against this task.. |
Démarrage Effectif | RW | The date on which the task is supposed to have started. When any update on the task is logged, it is deemed to have started. If actual start date was not specified, it defaults to the planned start date or the date of the update whichever is earlier. |
Fin Effective | RW | The date on which the task is supposed to have finished. When the task is marked as 100% complete, the actual finish date, if not specified, is update to the planned finish date or the date of the update whichever is earlier. |
Budget | RW | Task budget. Typically, Budget = Cout Planifié + Buffer. |
Cout de Non-Main doeuvre Planifiée | RW | The total estimated non-labor cost for this task. E.g. travel, food, software. |
Cout Fixe Planifié | RW | The cost that will be incurred on the task regardless of whether time is logged or expenses filled. |
Identifiant | R | The primary key of the task record in the database. |
Codes WBS | R | The Work Breakdown Structure (WBS) code of the task |
Démarrage Projeté | R | The date on which the task is expected to start based on the projected finish dates of its predecessors. |
Fin Projetée | R | The date on which the task is expected to finish based on its current rate of progress. For summary tasks, it is max of the finish dates of its leaf tasks. |
Jalon | R | A zero duration task. Read More. |
Critique | R | Indicates task is on a critical path. Read More. |
Effort Effectif | R | The sum of approved hours logged for this task. |
ProjectedHours | R | The total hours this task will require to finish based on the current rate of progress. Heures Projetées = Actual Hours ÷ % Complete. For summary tasks, it is the sum of projected hours of its leaf tasks. |
Heures Facturables Effectives | R | The total hours of approved and billable time logged on this task. |
Heures Non-Facturables Effectives | R | The total hours of approved and non-billable time logged on this task. This amount can be used to identify the "missed" billing opportunities for this task. |
Planned Cost | R | The total cost expected to be incurred on this task. Cout Planifié = Cout de Main doeuvre Planifiée + Cout de Non-Main doeuvre Planifiée + FixedCost |
Cout Effectif | R | The total cost incurred on the task so far. Cout Effectif = Cout de Main d’oeuvre Effectif + Cout de Non-Main d’oeuvre Effectif + Cout Fixe Effectif |
Cout Projeté | R | The expected total cost of a project based on its current rate of spend. |
Cout de Main d’oeuvre Effectif | R | The total of labor cost for each approved time entry logged on this task. |
Mise à jour (dernière) | R | The latest comment or progress update entered against a task. |
Revenu de Main doeuvre Planifiée | R | The sum of user's effort × user's bill rate for each resource assigned to this task. (Only available if you have user-based billing). |
Heures Facturées | R | The total time for all its invoiced time entries. |
Main d’oeuvre Facturée | R | The sum of the bill amounts for all its invoiced time entries. |
Dépense Facturée | R | The sum of all invoiced expenses for this task. |
Revenus Facturés | R | Main d’oeuvre Facturée + Dépense Facturée |
Ligne de Base % Terminé | R | The expected % complete of the task based on the baseline. |
Ligne de Base Budget | R | The budget of the task when it was baselined. |
Ligne de Base Cout | R | The planned cost of the task when it was baselined. |
Ligne de Base Effort | R | The planned effort when the task was baselined |
Écart Ligne de Base Effort | R | The difference between the planned and baseline effort |
Ligne de Base Démarrage | R | The task's planned start date when it was baselined. |
Écart Ligne de Base Démarrage | R | The difference between the task's planned and baseline start date. |
Ligne de Base Fin | R | The task's planned finish date when it was baselined. |
Écart Ligne de Base Fin | R | The difference between the task's planned and baseline finish date. |