Task Glossary


AttributeRead/WriteDescription
NomRWA short description.
Démarrage PlanifiéRWThe date at which the task is scheduled to start.
Fin PlanifiéeRWThe date at which the task is scheduled to finish.
Planifié ManuellementRWCeloxis will never change the start and finish of manually scheduled tasks. Read More.
DuréeRWThe duration of the task. It can be entered in these formats. Read More.
Effort PlanifiéRWThe total hours of effort required to complete the task. Read More.
Type de planificationRWOne of FixedEffort, Durée fixe, Unités fixes. Read More
Type de contrainte/Date de contrainteRWTask constraint. Not applicable for summary tasks and manually scheduled tasks. Read More.
RessourcesRWResources assigned on the task. It can be entered in this format.
% finRWThe percentage of work done. Read More.
% Terminé PlanifiéRWThe percentage that the task is expected to have completed by now. This value is an approximate value and will not be accurate if resources working on the task have working or non-working exceptions in the task duration.
PrioritéRWThe task's priority.
Permet la journalisation du tempsRWIndicates if time can be logged against this task..
Démarrage EffectifRWThe date on which the task is supposed to have started. When any update on the task is logged, it is deemed to have started. If actual start date was not specified, it defaults to the planned start date or the date of the update whichever is earlier.
Fin EffectiveRWThe date on which the task is supposed to have finished. When the task is marked as 100% complete, the actual finish date, if not specified, is update to the planned finish date or the date of the update whichever is earlier.
BudgetRWTask budget. Typically, Budget = Cout Planifié + Buffer.
Cout de Non-Main doeuvre PlanifiéeRWThe total estimated non-labor cost for this task. E.g. travel, food, software.
Cout Fixe PlanifiéRWThe cost that will be incurred on the task regardless of whether time is logged or expenses filled.
IdentifiantRThe primary key of the task record in the database.
Codes WBSRThe Work Breakdown Structure (WBS) code of the task
Démarrage Projeté RThe date on which the task is expected to start based on the projected finish dates of its predecessors.
Fin ProjetéeRThe date on which the task is expected to finish based on its current rate of progress. For summary tasks, it is max of the finish dates of its leaf tasks.
JalonRA zero duration task. Read More.
CritiqueR Indicates task is on a critical path. Read More.
Effort EffectifRThe sum of approved hours logged for this task.
ProjectedHoursRThe total hours this task will require to finish based on the current rate of progress. Heures Projetées = Actual Hours ÷ % Complete. For summary tasks, it is the sum of projected hours of its leaf tasks.
Heures Facturables EffectivesRThe total hours of approved and billable time logged on this task.
Heures Non-Facturables EffectivesRThe total hours of approved and non-billable time logged on this task. This amount can be used to identify the "missed" billing opportunities for this task.
Planned Cost RThe total cost expected to be incurred on this task. Cout Planifié = Cout de Main doeuvre Planifiée + Cout de Non-Main doeuvre Planifiée + FixedCost
Cout EffectifRThe total cost incurred on the task so far. Cout Effectif = Cout de Main d’oeuvre Effectif + Cout de Non-Main d’oeuvre Effectif + Cout Fixe Effectif
Cout ProjetéRThe expected total cost of a project based on its current rate of spend.
Cout de Main d’oeuvre EffectifRThe total of labor cost for each approved time entry logged on this task.
Mise à jour (dernière)RThe latest comment or progress update entered against a task.
Revenu de Main doeuvre PlanifiéeRThe sum of user's effort × user's bill rate for each resource assigned to this task. (Only available if you have user-based billing).
Heures FacturéesRThe total time for all its invoiced time entries.
Main d’oeuvre FacturéeRThe sum of the bill amounts for all its invoiced time entries.
Dépense Facturée RThe sum of all invoiced expenses for this task.
Revenus FacturésRMain d’oeuvre Facturée + Dépense Facturée
Ligne de Base % TerminéRThe expected % complete of the task based on the baseline.
Ligne de Base Budget RThe budget of the task when it was baselined.
Ligne de Base Cout RThe planned cost of the task when it was baselined.
Ligne de Base EffortRThe planned effort when the task was baselined
Écart Ligne de Base EffortRThe difference between the planned and baseline effort
Ligne de Base DémarrageRThe task's planned start date when it was baselined.
Écart Ligne de Base DémarrageRThe difference between the task's planned and baseline start date.
Ligne de Base FinRThe task's planned finish date when it was baselined.
Écart Ligne de Base FinRThe difference between the task's planned and baseline finish date.